Bldg. 18 - Building Power Shutdown Request #5

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 7 11:49:18 2002

Message-ID: <568F0AEE7A57D511923900508B5564511563F1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rjwilk@mit.edu'" <rjwilk@mit.edu>,
        "'rdevito@linbeck.com'"
	 <rdevito@linbeck.com>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'opsnote@mit.edu'" <opsnote@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 7 Feb 2002 11:49:17 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	rjwilk@mit.edu; rdevito@linbeck.com; shutdowns@mit.edu;
> opsnote@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 18 - Building Power Shutdown Request #5
> 
> 
The following building power shutdown request #5 for Bldg. 18 - 1st and 2nd
floor Labs A, B, C, D, Electric Room., Telephone Room and shafts 2 and 3 on
Friday, 2/15 is for your review and comment.  Would you please let me know
whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Critical
> Building: 18 - 1st and 2nd floor Labs A, B, C, D, Electric Room.,
> Telephone Room and shafts 2 and 3
> Date: 2/15/2002
> Day: Friday
> Time: 6 AM  - 8 AM
> System: Building Power 120V - 208V Panels L1A, L1B, L1C, L1D, L104, L2A,
> L2B, L2C and L2D
> Duration: 2 hours
> Reason: 
> Swapping feeds to power panels.
> 
> Effect: 
> Loss of building power to the following rooms in Bldg. 18 - 1st and 2nd
> floor labs, A, B, C, D, Electric Rm. Tel. Rm. and Shafts 2 and 3 during
> the 2-hour shutdown period.
> 
> 