Bldg. 18 - Critical Building Power Shutdown Request #3

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 7 11:09:56 2002

Message-ID: <568F0AEE7A57D511923900508B5564511563ED@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rjwilk@mit.edu'" <rjwilk@mit.edu>,
        "'rdevito@linbeck.com'"
	 <rdevito@linbeck.com>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'opsnote@mit.edu'" <opsnote@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 7 Feb 2002 11:09:54 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	rjwilk@mit.edu; rdevito@linbeck.com; shutdowns@mit.edu;
> opsnote@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 18 - Critical Building Power Shutdown Request #3
> 
> 
The following Critical building power shutdown request #3 for Bldg. 18 - 4th
floor labs, A, B, C, D, Electric Rm., Tel. Rm. Shafts 2 and 3 and South End
Lab, 4th floor on Wednesday, 2/13 is for your information.  Would you please
let me know whether this does or does not have your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872 

> Status: Critical
> Building:  18 - 4th floor labs, A, B, C, D, Electric Rm., Tel. Rm. Shafts
> 2 and 3 and South End Lab , 4th floor 
> Date: 2/13/2002
> Day: Wednesday
> Time: 6 AM - 8 AM
> System: Building Power 120-208V, Panels L4A, L4B, L4C, L4D and L4S
> Duration: 2  hours
> Reason: 
> Swapping feeds to power panels.
> 
> Effect: 
> Loss of building power in the above listed areas during the 2-hour
> shutdown period.
> 
> 