[57902] in Hotline Meeting
Bldg. 10 - Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jan 14 15:25:47 2002
Message-ID: <568F0AEE7A57D511923900508B556451156250@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jgk@mit.edu'" <jgk@mit.edu>, "'tr6@mit.edu'" <tr6@mit.edu>,
"'jdoucett@mit.edu'" <jdoucett@mit.edu>,
"'tdoyle@mit.edu'"
<tdoyle@mit.edu>, C-Zone <C-Zone@mit.edu>,
"'johnnyd@mit.edu'"
<johnnyd@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Paul Rudack
<PRudack@PLANT.MIT.EDU>
Date: Mon, 14 Jan 2002 15:25:44 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: jgk@mit.edu; tr6@mit.edu; jdoucett@mit.edu; tdoyle@mit.edu; C-Zone;
> johnnyd@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Paul Rudack
> Subject: Bldg. 10 - Asbestos Removal Notification
>
>
The following asbestos removal notification for Bldg 10 - 050 on Tuesday,
1/22 AM through Thursday, 1/24 is for your information. If you have any
question about this, please contact Paul Rudack at x2-1482.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 10 - 050
> Date: 1/22/2002
> Day: Tuesday
> Time: 7 AM (1/22) - 4 PM (1/24)
> System: None - asbestos removal notification only
> Duration: 57 hours
> Reason:
> Must remove 1,000 to 1,500 square feet of floor tile in 10-050.
>
> Effect:
> No access to 10-050 during the asbestos removal period.
>
>