[57898] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 13 - Elevator Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jan 14 13:34:34 2002

Message-ID: <568F0AEE7A57D511923900508B556451156248@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'generoso@mit.edu'" <generoso@mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 14 Jan 2002 13:34:29 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	generoso@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 13 - Elevator Shutdown Request
> 
> 
The following elevators shutdown request (both passenger and freight) for
Bldg. 13 on Friday, 1/18 is for your information and comment. Would you
please let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Emergency
> Building: 13 
> Date: 1/18/2002
> Day: Friday
> Time: 7 AM - 11 AM
> System: Elevators - freight and passenger
> Duration: 4 hours
> Reason: 
> To complete the elevator recall connections for passenger elevators and
> shunt trip test on freight elevator.
> 
> Effect: 
> Minimal - the elevators will be down one elevator at a time in sequence.
> One can also use the elevators in Bldg. 10 to access Bldg. 13. 
> 
> 

home help back first fref pref prev next nref lref last post