[57820] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 36 - Air Handler 8 Altered Schedule of Operation

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jan 8 10:26:18 2002

Message-ID: <568F0AEE7A57D511923900508B5564511561D4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>, B-Zone <B-Zone@mit.edu>,
        Cust-Coach
	 <cust-coach@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
        "'nmorriso@mit.edu'"
	 <nmorriso@mit.edu>,
        "'rpc@mit.edu'" <rpc@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        Operators
	 <Operators@PLANT.MIT.EDU>
Date: Tue, 8 Jan 2002 10:26:14 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	amcgurl@rle.mit.edu; shutdowns@mit.edu; B-Zone; Cust-Coach;
> schedule@mit.edu; wrgibbs@rle.mit.edu; nmorriso@mit.edu; rpc@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: 	Bldg. 36 - Air Handler 8 Altered Schedule of Operation
> 
> 
The following altered schedule of operation for Bldg. 36 - Floors 2 - 8
South Side, Air Handler 8 beginning Tuesday, 1/8 at 6:30 AM to Saturday,
March 2 at 5:30 PM is for your information.  If you have any question about
this, please contact Bob Cunkelman at 3-6371.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 36 - floors 2 - 8 South Side
> Date: 1/8/2002
> Day: Tuesday
> Time: 6:30 AM - 5:30 PM each day
> System: Air Handler 8
> Duration: 9 hours each day
> Reason: 
> To prevent containment of diesel exhaust from construction activities.
> 
> Effect: 
> Loss of supply ventilation and supply heating in 36 - floors 2 - 8 South
> Side between 6:30 AM - 5:30 PM each day.  If there is a problem concerning
> temperatures in the building between the shutdown hours, please contact
> the Operations Center at 3-1500 to report it. The Operations Center can
> alter the temperature within the building. 
> 
> 

home help back first fref pref prev next nref lref last post