[57783] in Hotline Meeting
Bldg. 36 - Air Handler 8 Shutdown Test
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 3 14:53:46 2002
Message-ID: <568F0AEE7A57D511923900508B556451156190@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
Operators
<Operators@PLANT.MIT.EDU>,
"'nmorriso@mit.edu'" <nmorriso@MIT.Edu>, "'rpc@mit.edu'" <rpc@MIT.Edu>
Date: Thu, 3 Jan 2002 14:53:37 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: amcgurl@rle.mit.edu; B-Zone; Cust-Coach; schedule@mit.edu;
> wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators;
> nmorriso@mit.edu; rpc@mit.edu
> Subject: Bldg. 36 - Air Handler 8 Shutdown Test
>
>
The following Air Handler 8 shutdown request for Bldg. 36 - South Side -
Floors 2 through 8 on Friday, 1/4 is for your information. If you have any
question about this, please contact Bob Cunkelman at 3-6371.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 36 - South Side - Floors 2 through 8
> Date: 1/4/2002
> Day: Friday
> Time: 5 AM - 3 PM
> System: Air Handler 8
> Duration: 10 hours
> Reason:
> Testing the ability of the perimeter baseboard system to provide adequate
> heat, without the Air Handler Unit operating.
>
> Effect:
> Loss of supply ventilation and supply heating in 36 - south side - floors
> 2 through 8 during the testing period. It is hoped the ability of the
> perimeter baseboard system will provide adequate heat.
>
>