[57743] in Hotline Meeting
Bldg. E25 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Dec 28 11:31:56 2001
Message-ID: <568F0AEE7A57D511923900508B556451156140@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andrea@psyche.mit.edu'" <andrea@psyche.mit.edu>,
"'arolle@mit.edu'"
<arolle@mit.edu>,
"'bengel@mit.edu'" <bengel@mit.edu>,
"'cpoon@mit.edu'"
<cpoon@mit.edu>, E-Zone <E-Zone@mit.edu>,
"'elworthi@mit.edu'"
<elworthi@mit.edu>,
"'hegarty@mit.edu'" <hegarty@mit.edu>,
"'jmganno@mit.edu'" <jmganno@mit.edu>,
"'jrauch@mit.edu'"
<jrauch@mit.edu>,
"'loudib@mit.edu'" <loudib@mit.edu>,
"'rfink@mit.edu'"
<rfink@mit.edu>,
"'roge@med.mit.edu'" <roge@med.mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sdalton@mit.edu'"
<sdalton@mit.edu>,
"'sdl-adm-lib@mit.edu'" <sdl-adm-lib@mit.edu>,
"'shyoung@mit.edu'" <shyoung@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: Doug Boyer <dboyer@PLANT.MIT.EDU>,
Joseph Ficarra
<jficarra@PLANT.MIT.EDU>,
RM-TechTeam <rm-techteam@mit.edu>,
"'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 28 Dec 2001 11:30:30 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: andrea@psyche.mit.edu; arolle@mit.edu; bengel@mit.edu;
> cpoon@mit.edu; E-Zone; elworthi@mit.edu; hegarty@mit.edu; jmganno@mit.edu;
> jrauch@mit.edu; loudib@mit.edu; rfink@mit.edu; roge@med.mit.edu;
> schedule@mit.edu; sdalton@mit.edu; sdl-adm-lib@mit.edu; shyoung@mit.edu;
> shutdowns@mit.edu
> Cc: Doug Boyer; Joseph Ficarra; RM-TechTeam; shutdown@plant.mit.edu
> Subject: Bldg. E25 - Building Power Shutdown Request
>
>
The following building power shutdown request for Bldg. E25 - 1st floor on
either Wednesday, 1/2/02 or Friday, January 4, 2001 is for your review and
comment. Would you please let me know whether this does or does not have
your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E25 - 1st floor
> Date: 1/2/2002
> Day: Wednesday
> Time: 6:30 AM - 7:00 AM
> System: Building Power/Power source for panel DPLA1A in 059E and DPL ABA
> Cir. #1
> Duration: 30 minutes
> Reason:
> Make permanent power connections to panel DPLA-1-A for renovation at
> loading dock.
>
> Effect:
> Affects Feeder Panels APLA1A and APLA1B. This affects the vestibule
> heating outside 143; the air conditioning unit in Room 143; the Computer
> room in 143, the receptacles in Mail Room 143; Solvent Storage Room in
> 143; red lights in 147; Andover Controls VAVBoxes; Receptacles and lights
> in Room 143; Receptacles and lights in 131 A & B, Receptacles and lights
> in 135, Receptacles and lights in 137, Receptacles and lights in the
> Atrium Bridge on the 1st - 5th floors; Auditorium lighting and the
> Receiving Door during the 30 minutes shutdown period.
>
>