[57724] in Hotline Meeting
Bldg. 39 - Air Handler 2 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Dec 21 14:32:26 2001
Message-ID: <568F0AEE7A57D511923900508B55645115611E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'armay@mit.edu'" <armay@mit.edu>, B-Zone <B-Zone@mit.edu>,
Cust-Coach
<cust-coach@mit.edu>, George Mac Leod <gmacleod@mit.edu>,
"'mcgrath@mtl.mit.edu'" <mcgrath@mtl.mit.edu>,
"'rcf@space.mit.edu'"
<rcf@space.mit.edu>,
"'walsh@mtl.mit.edu'" <walsh@mtl.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 21 Dec 2001 14:30:59 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: armay@mit.edu; B-Zone; Cust-Coach; George Mac Leod;
> mcgrath@mtl.mit.edu; rcf@space.mit.edu; walsh@mtl.mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 39 - Air Handler 2 Shutdown Request
>
>
The following Air Handler 2 shutdown request for Bldg. 39 - Clean Rooms on
Wednesday, 12/26 is for your information and comment. Would you please let
me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 39 - Clean Rooms
> Date: 12/26/2001
> Day: Wednesday
> Time: 7;30 AM - 9:30 AM
> System: Air Handler 2/Supply Air
> Duration: 2 hours
> Reason:
> To replace in duct smoke detector.
>
> Effect:
> Loss of supply ventilation in Bldg. 39 Clean Rooms during the 2-hour
> shutdown period.
>
>