[57436] in Hotline Meeting
Bldg. W20 - Air Handler 5/Supply Cooling Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 27 11:32:56 2001
Message-ID: <568F0AEE7A57D511923900508B556451155FBD@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'capone@mit.edu'" <capone@mit.edu>, D-Zone <D-Zone@mit.edu>,
"'eisen@mit.edu'" <eisen@mit.edu>, "'flett@mit.edu'" <flett@mit.edu>,
"'lsc@mit.edu'" <lsc@mit.edu>, "'mwf@mit.edu'" <mwf@mit.edu>,
"'pdc@mit.edu'" <pdc@mit.edu>, "'pwalsh@mit.edu'" <pwalsh@mit.edu>,
"'rberlin@mit.edu'" <rberlin@mit.edu>,
"'sdimond@mit.edu'"
<sdimond@mit.edu>,
"'wganger@mit.edu'" <wganger@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 27 Nov 2001 11:32:43 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: capone@mit.edu; D-Zone; eisen@mit.edu; flett@mit.edu; lsc@mit.edu;
> mwf@mit.edu; pdc@mit.edu; pwalsh@mit.edu; rberlin@mit.edu;
> sdimond@mit.edu; wganger@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. W20 - Air Handler 5/Supply Cooling Shutdown Request
>
>
The following Air Handler 5/Supply Fan 5 - Supply Cooling shutdown request
for Bldg. W20 - 1st floor Retail Stores on Wednesday, 12/5 is for your
information and comment. Would you please let me know whether this does or
does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: W20 - 1st floor Retail Stores
> Date: 12/5/2001
> Day: Wednesday
> Time: 7 AM - 3 PM
> System: Air Handler 5 and Supply Cooling
> Duration: 8 hours
> Reason:
> To replace Air Handler 5 chilled water coil isolation valves.
>
> Effect:
> Loss of Air Handler 5/Supply Fan 5 - supply cooling in W20 - 1st floor
> Retail Stores during the shutdown period.
>
>