RE: Shutdown request for E19-207 A, B, &C, 215G, 222A, 224C on 11

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Nov 26 07:28:00 2001

Message-ID: <568F0AEE7A57D511923900508B556451B5418B@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: bengel@mit.edu, cschultz@mit.edu, dcairns@mit.edu, dlking@mit.edu,
        dshea@mit.edu, dturn@mit.edu, E-Zone <E-Zone@mit.edu>, e19site@mit.edu,
        elsagt@mit.edu, esico@mit.edu, hallisey@mit.edu, honiker@mit.edu,
        joconor@mit.edu, kelley@mit.edu, kshooter@mit.edu,
        lambert@mitvma.mit.edu, mbowers@mit.edu,
        Michael Sherman <MSherman@PLANT.MIT.EDU>,
        Mary Tobin
	 <mtobin@PLANT.MIT.EDU>, narbonne@mit.edu, opsnote@mit.edu,
        rberlin@mit.edu, safety@mit.edu, sfalconi@mit.edu,
        Steve Miscowski
	 <SMiscows@PLANT.MIT.EDU>, tdalton@mit.edu,
        tmeehan@mit.edu, wbarrett@mit.edu, wganger@mit.edu, schedule@mit.edu,
        shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 26 Nov 2001 07:21:26 -0500
MIME-Version: 1.0
Content-Type: text/plain

This shutdown is being rescheduled.  You will be notified shortly about the
new date and time.

Thank you
Dawn Simonelli
Repair and Maintenance



 E19-207 A, B, &C, 215G, 222A, 224C on 11/26- 11/28

> Status: Normal
> Building: E19-207 A, B, &C, 215G, 222A, 224C 
> Date: 11/26/2001
> Day: Monday
> Time: 7am - 3pm each day
> System: Chilled water
> Duration: 3 days
> Reason: 
> Installing new fan coil units.
> 
> Effect: 
> There will be no chilled water during this time.
> 
> 