[57389] in Hotline Meeting

home help back first fref pref prev next nref lref last post

RE: Shutdown request for building 13 on 11/27 & 11/28

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Nov 21 14:56:33 2001

Message-ID: <568F0AEE7A57D511923900508B556451B54154@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: Dawn Simonelli <dsimone@PLANT.MIT.EDU>, B-Zone <B-Zone@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, elk@MIT.Edu, schedule@MIT.Edu,
        src@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Wed, 21 Nov 2001 14:56:31 -0500
MIME-Version: 1.0
Content-Type: text/plain

I am sorry this elevator will be shutdown only from 7am - 10 am on each day.
November 27 & 28.

Thank you
Dawn Simonelli
Repair and Maintenance


-----Original Message-----
From: Dawn Simonelli [mailto:dsimone@PLANT.MIT.EDU]
Sent: Wednesday, November 21, 2001 2:54 PM
To: B-Zone; Cust-Coach; elk@MIT.Edu; schedule@MIT.Edu; src@MIT.Edu;
shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Subject: Shutdown request for building 13 on 11/27 & 11/28


> To: 	B-Zone; Cust-Coach; elk@mit.edu; schedule@mit.edu; src@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	 Shutdown request for building 13 on 11/27 & 11/28
> 
> 
The following shutdown request is for building 13 on 11/27 & 11/28.  Please
let me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: 13
> Date: 11/27/2001
> Day: Tuesday
> Time: 7am 11/27 - 10am 11/28
> System: Passenger elevator
> Duration: 2 days
> Reason: 
> Fire alarm testing of the elevator.  Recall.
> 
> Effect: 
> The passenger elevator will be shutdown for this time.
> 
> 