[57300] in Hotline Meeting
Bldg. 13 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Nov 15 08:28:57 2001
Message-ID: <568F0AEE7A57D511923900508B556451155F47@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'elk@mit.edu'" <elk@mit.edu>, "'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 15 Nov 2001 08:28:54 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: elk@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 13 - Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. 13 - 1150A East on
Monday, 11/19, Tuesday, 11/20 and Wednesday, 11/21 is for your reviwe and
comment. Would you please let me know whether this does or does not have
your approval.
Thank you Ed.
Andrea Nichols
Repair and Maintenace
8-7872
> Status: Normal
> Building: 13 - 1150A East
> Date: 11/19/2001
> Day: Monday
> Time: 6 AM - 2 PM each day
> System: Chilled water
> Duration: 8 hours each day for 3 days
> Reason:
> Relocate existing chilled water to accommodate mechanicals.
>
> Effect:
> Loss of chilled water (air conditioning) in 1150A East during the 8-hour
> each day/3-day shutdown period.
>
>