[57286] in Hotline Meeting
Bldg. 13 - Air Handler 3 Revised Shutdown Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 14 10:38:27 2001
Message-ID: <568F0AEE7A57D511923900508B556451155F30@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'elk@mit.edu'" <elk@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'src@mit.edu'" <src@mit.edu>, "'rpc@mit.edu'"
<rpc@mit.edu>,
B-Zone <B-Zone@mit.edu>, Scott Brenner
<sbrenner@PLANT.MIT.EDU>,
"Brian O'Keefe" <bokeefe@PLANT.MIT.EDU>,
"'nmorriso@mit.edu'" <nmorriso@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Wed, 14 Nov 2001 10:38:14 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: elk@mit.edu; Cust-Coach; shutdowns@mit.edu; schedule@mit.edu;
> src@mit.edu; rpc@mit.edu; B-Zone; Scott Brenner; Brian O'Keefe;
> nmorriso@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. 13 - Air Handler 3 Revised Shutdown Notification
>
>
The following revised shutdown request for Bldg. 13 - 1150A (Air Handler 3 -
Perimeter heat) is now on Thursday, 11/15 is again for your review and
information. If you have any concern about this, please contact Bob
Cunkelman at 3-6371.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 13 - 1150A
> Date: 11/15/2001
> Day: Thursday
> Time: 6 AM - 12 midnight
> System: Air Handler 3 (supply ventilation, supply cooling, supply heating)
> Duration: 16 hours
> Reason:
> Relocate existing duct to accommodate new duct.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in 13-1150A
> during the shutdown period. The temperature outside tomorrow is supposed
> to be 60 degrees.
>
>