[57239] in Hotline Meeting
Bldg. 14 - Air Handlers 1, 2, 3 and 5 Critical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 9 13:42:20 2001
Message-ID: <568F0AEE7A57D511923900508B556451155F07@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'altenb@mit.edu'" <altenb@MIT.Edu>,
"'bkdavis@mit.edu'" <bkdavis@MIT.Edu>,
"'cpomieko@mit.edu'"
<cpomieko@MIT.Edu>,
"'csnyder@mit.edu'" <csnyder@MIT.Edu>,
Cust-Coach
<cust-coach@MIT.Edu>,
"'edorsch@mit.edu'" <edorsch@MIT.Edu>,
"'ellertsn@mit.edu'" <ellertsn@MIT.Edu>,
"'jhlyons@mit.edu'"
<jhlyons@MIT.Edu>,
"'jmullins@mit.edu'" <jmullins@MIT.Edu>,
"'mosh@mit.edu'" <mosh@MIT.Edu>, "'nlowe@mit.edu'" <nlowe@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@MIT.Edu>,
"'slarkin@mit.edu'" <slarkin@MIT.Edu>,
"'susanne@mit.edu'" <susanne@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 9 Nov 2001 13:42:17 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; altenb@mit.edu; bkdavis@mit.edu; cpomieko@mit.edu;
> csnyder@mit.edu; Cust-Coach; edorsch@mit.edu; ellertsn@mit.edu;
> jhlyons@mit.edu; jmullins@mit.edu; mosh@mit.edu; nlowe@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; slarkin@mit.edu; susanne@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 14 - Air Handlers 1, 2, 3 and 5 Critical Shutdown
> Request
>
>
The following Critical shutdown request for Bldg. 14 -East Wing, 1st, 2nd,
3rd floor, basement, South Wing East and Killian Hall on Monday, 11/12 PM to
Tuesday, 11/13 AM is for your review and comment. Would you please let me
know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Critical
> Building: 14 - East Wing, Basement, 1, 2, 3 floors, South Wing East,
> Killian Hall
> Date: 11/12/2001
> Day: Monday
> Time: 10 PM (11/12) - 7 AM (11/13)
> System: Air Handlers 1, 2, 3 and 5
> Duration: 8 hours
> Reason:
> Replace panels for above listed fans.
>
> Effect:
> Loss of supply ventilation, supply cooling, supply heating in the above
> listed areas during the 8-hour shutdown period.
>
>