[57223] in Hotline Meeting
Bldg. 66 - Critical All Normal Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Nov 8 11:35:33 2001
Message-ID: <568F0AEE7A57D511923900508B556451155EE5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'swetzel@mit.edu'" <swetzel@mit.edu>,
"'patsys@mit.edu'"
<patsys@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
James Sullivan
<jsulliva@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
Steven Gilligan <sgilliga@PLANT.MIT.EDU>
Date: Thu, 8 Nov 2001 11:35:28 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: swetzel@mit.edu; patsys@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu; James Sullivan; Manuel Moreira; Steven
> Gilligan
> Subject: Bldg. 66 - Critical All Normal Building Power Shutdown
> Request
>
>
The following Critical all normal building power shutdown request for Bldg.
66 on Thursday, 11/15 PM to Friday, 11/16 AM is for your information and
comment. Would you please let me know whether this does or does not have
your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Critical
> Building: 66
> Date: 11/15/2001
> Day: Thursday
> Time: 10 PM (11/15) - 6 AM (11/16)
> System: All normal building power
> Duration: 8 hours
> Reason:
> Emergency preventive maintenance of switchgear and breakers.
>
> Effect:
> Loss of all normal building power: access controls (anything that is
> plugged into an outlet), computers and lighting. The Emergency Power will
> remain on during the shutdown period.
>
>