[57220] in Hotline Meeting
Bldgs. 34, 36 and 38 Emergency - Emergency Power Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Nov 8 11:04:49 2001
Message-ID: <568F0AEE7A57D511923900508B556451155EE1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'rroscoe@mit.edu'" <rroscoe@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>,
"'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
"'agallant@mit.edu'"
<agallant@MIT.Edu>,
"'pmorley@mit.edu'" <pmorley@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'nmorriso@mit.edu'"
<nmorriso@MIT.Edu>,
James Sullivan <jsulliva@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
Paul Stordy
<PStordy@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>
Date: Thu, 8 Nov 2001 11:04:46 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; rroscoe@mit.edu; schedule@mit.edu;
> amcgurl@rle.mit.edu; wrgibbs@rle.mit.edu; agallant@mit.edu;
> pmorley@mit.edu; shutdowns@mit.edu; nmorriso@mit.edu; James Sullivan;
> Manuel Moreira; Paul Stordy
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldgs. 34, 36 and 38 Emergency - Emergency Power Shutdown
>
>
The following Emergency shutdown request for Emergency Power in Bldgs. 34,
36 and 38 on Friday, 11/9 is for your information. If you have any question
about this, please contact Paul Stordy at 8-9174.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Emergency
> Building: 34, 36 and 38
> Date: 11/9/2001
> Day: Friday
> Time: 6 AM - 7 AM
> System: Emergency Power
> Duration: 1 hour
> Reason:
> Repair emergency power to normal power transfer switch.
>
> Effect:
> Loss of emergency power which affects lighting in corridors/stairs;
> Drainage: lab waste and sanitary during the 1-hour shutdown period. Normal