Bldg. 26 - Main Steam & Control Air Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 7 11:16:09 2001

Message-ID: <568F0AEE7A57D511923900508B556451155EC2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, "'dudley@mit.edu'" <dudley@MIT.Edu>,
        "'kates@mit.edu'" <kates@MIT.Edu>,
        "'khewitt@mit.edu'" <khewitt@MIT.Edu>,
        "'ljtrudel@mit.edu'" <ljtrudel@MIT.Edu>, "'lsc@mit.edu'" <lsc@MIT.Edu>,
        "'mhankin@mit.edu'" <mhankin@MIT.Edu>,
        "'nsteele@mit.edu'"
	 <nsteele@MIT.Edu>,
        "'safety@mit.edu'" <safety@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'trobins@mit.edu'"
	 <trobins@MIT.Edu>,
        "'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 7 Nov 2001 11:16:03 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	amcgurl@rle.mit.edu; B-Zone; Cust-Coach; dudley@mit.edu;
> kates@mit.edu; khewitt@mit.edu; ljtrudel@mit.edu; lsc@mit.edu;
> mhankin@mit.edu; nsteele@mit.edu; safety@mit.edu; schedule@mit.edu;
> trobins@mit.edu; wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 26 - Main Steam & Control Air Shutdown Request
> 
> 
The following Main Steam and Control Air shutdown request for Bldg. 26 on
Saturday, 11/17 is for your information and comment.  Would you please let
me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 26
> Date: 11/17/2001
> Day: Saturday
> Time: 7 AM - 3 PM
> System: Main Steam and Control air (result in loss of supply ventilation,
> supply cooling and supply heating)
> Duration: 8 hours
> Reason: 
> Repair leaking dresser couplings on Main Condensate receiver tank and
> replace control air receiver tank.
> 
> Effect: 
> Loss of main steam and compressed control and compressed lab air. This
> results in loss of supply ventilation, supply cooling and supply heating
> in Bldg. 26 during the shutdown period.
> 
> 