Shutdown request for E15 on 11/7/01
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Nov 5 10:19:37 2001
Message-ID: <568F0AEE7A57D511923900508B556451B53653@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: barbra@media.mit.edu, E-Zone <E-Zone@MIT.Edu>, fresina@media.mit.edu,
haller@media.mit.edu, heine@media.mit.edu, kdavis@media.mit.edu,
tragert@media.mit.edu, shutdowns@MIT.Edu, schedule@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 5 Nov 2001 10:19:35 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: barbra@media.mit.edu; E-Zone; fresina@media.mit.edu;
> haller@media.mit.edu; heine@media.mit.edu; kdavis@media.mit.edu;
> tragert@media.mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for E15 on 11/7/01
>
>
The following shutdown request is for building E15 on 11/7. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Normal
> Building: E15
> Date: 11/7/2001
> Day: Wednesday
> Time: 7 am - 3 pm
> System: Smoke Detectors
> Duration: 8 hours
> Reason:
> There will be welding being done in the area.
>
> Effect:
> The fire alarms and smoke detectors will be down during this time.
>
>