[57157] in Hotline Meeting
14W shutdown request for 11/12
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Nov 5 09:53:40 2001
Message-ID: <568F0AEE7A57D511923900508B556451B53644@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, altenb@MIT.Edu, bkdavis@MIT.Edu, cpomieko@MIT.Edu,
csnyder@MIT.Edu, Cust-Coach <cust-coach@MIT.Edu>, edorsch@MIT.Edu,
ellertsn@MIT.Edu, jhlyons@MIT.Edu, jmullins@MIT.Edu, mosh@MIT.Edu,
nlowe@MIT.Edu, schedule@MIT.Edu, sdl-adm-lib@MIT.Edu, slarkin@MIT.Edu,
susanne@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 5 Nov 2001 09:53:36 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; altenb@mit.edu; bkdavis@mit.edu; cpomieko@mit.edu;
> csnyder@mit.edu; Cust-Coach; edorsch@mit.edu; ellertsn@mit.edu;
> jhlyons@mit.edu; jmullins@mit.edu; mosh@mit.edu; nlowe@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; slarkin@mit.edu; susanne@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: 14W shutdown request for 11/12
>
>
The following shutdown request is for building 14W on 11/12. Please let me
know if this does or does not have your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Normal
> Building: 14W
> Date: 11/12/2000
> Day: Monday
> Time: 10 pm - 7 am
> System: AH4, SF4, and RF4
> Duration: 9 hours
> Reason:
> Installing a new motor control and new wiring.
>
> Effect:
> There will be a loss of supply air ventilation, supply air cooling, and
> supply air heating.
>
>