[57140] in Hotline Meeting
Bldg. NW21 - Smoke Detector Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 2 10:23:33 2001
Message-ID: <568F0AEE7A57D511923900508B556451155E7D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.Edu>, "'fulton@psfc.mit.edu'" <fulton@psfc.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 2 Nov 2001 10:23:31 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: D-Zone; fulton@psfc.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. NW21 - Smoke Detector Shutdown Request
>
>
The following smoke detector shutdown request for Bldg. NW21 from Monday,
11/5 through Wednesday, 11/21 (weekdays only & excluding Veteran's Day
Holiday) is for your information and comment. Would you please let me know
whether this does or does not meet witn your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: NW21
> Date: 11/5/2001
> Day: Monday
> Time: 7 AM - 3 PM each day
> System: Smoke Detectors/Air Handler/Supply Fan 1 & area of crawl space
> around Rm. 156
> Duration: 8 hours each day for 12 days
> Reason:
> Welding in crawlspace.
>
> Effect:
> Loss of smoke detectors during the 12-day shutdown period. The Safety
> Office will be advised of this.
>
>