[57102] in Hotline Meeting
Bldg. 66 - Approved Building Power Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 31 10:38:04 2001
Message-ID: <568F0AEE7A57D511923900508B556451155E44@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-Utl <rm-utl@mit.edu>, "'ghand@mit.edu'" <ghand@mit.edu>,
Paul Stordy <PStordy@PLANT.MIT.EDU>,
James Sullivan
<jsulliva@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
Steven Gilligan <sgilliga@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>,
Cust-Coach <cust-coach@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Date: Wed, 31 Oct 2001 10:38:00 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: RM-Utl; ghand@mit.edu; Paul Stordy; James Sullivan; Manuel Moreira;
> Steven Gilligan
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Billy Homeyer;
> Cust-Coach; shutdowns@mit.edu
> Subject: Bldg. 66 - Approved Building Power Shutdown
>
>
The following approved building power shutdown for Bldg. 66 on Thursday,
11/1 PM to Friday, 11/2 AM is for your information. The building will be
closed during the power outage.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 66 - building to be closed during power shutdown
> Date: 11/1/2001
> Day: Thursday
> Time: 11 PM (11/1) - 7 AM (11/2)
> System: Building Power
> Duration: 8 hours
> Reason:
> Replacing main breaker, running new feed to subbasement.
>
> Effect:
> Loss of building power: access controls, elevators, computers,
> lighting-corridors/stairs; Air: supply ventilation, exhaust-laboratory,
> exhaust-general and exhaust-toilet air. Emergency power will remain
> available however.
>
>