Bldg. 66 - Asbestos Removal Notification

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 31 09:27:08 2001

Message-ID: <568F0AEE7A57D511923900508B556451155E40@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patsys@mit.edu'" <patsys@mit.edu>,
        "'swetzel@mit.edu'"
	 <swetzel@mit.edu>,
        "'kkgleasn@mit.edu'" <kkgleasn@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>, A-Zone <A-Zone@mit.edu>,
        Tim Donaghey
	 <TDonaghe@PLANT.MIT.EDU>, "'tr6@mit.edu'" <tr6@mit.edu>,
        "'jdoucett@mit.edu'" <jdoucett@mit.edu>,
        "'tdoyle@mit.edu'"
	 <tdoyle@mit.edu>,
        Jack Allen <jrallen@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        "'nmorriso@mit.edu'"
	 <nmorriso@mit.edu>
Date: Wed, 31 Oct 2001 09:26:55 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	patsys@mit.edu; swetzel@mit.edu; kkgleasn@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; A-Zone; Tim Donaghey; tr6@mit.edu; jdoucett@mit.edu;
> tdoyle@mit.edu; Jack Allen
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; nmorriso@mit.edu
> Subject: 	Bldg. 66 - Asbestos Removal Notification
> 
> 
The following asbestos removal notification for Bldg. 66 - 201 on Wednesday,
11/7 AM through Friday, 11/9 PM is for your information.  If you have any
question about this, please contact Tammy Doyle at 3-5166 or Jack Allen at
3-6352.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 66 - 201
> Date: 11/7/2001
> Day: Wednesday
> Time: 7 AM (11/7) - 4 PM (11/9)
> System: None - asbestos removal
> Duration: 57 hours
> Reason: 
> Must remove 110 square feet of floor tile in 66 - 201.
> 
> Effect: 
> No access to 66 - 201 during the asbestos removal period.
> 
> 