Bldg. 1 - Asbestos Removal Notification

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 31 09:02:56 2001

Message-ID: <568F0AEE7A57D511923900508B556451155E3E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'dfucillo@mit.edu'" <dfucillo@MIT.Edu>,
        "'fenner@mit.edu'"
	 <fenner@MIT.Edu>,
        "'magowen@mit.edu'" <magowen@MIT.Edu>,
        "'mamullow@mit.edu'" <mamullow@MIT.Edu>,
        "'mgibson@mit.edu'"
	 <mgibson@MIT.Edu>,
        "'patdixon@mit.edu'" <patdixon@MIT.Edu>,
        "'rlbras@mit.edu'" <rlbras@MIT.Edu>,
        "'schedule@mit.edu'"
	 <schedule@MIT.Edu>,
        "'scottc@mit.edu'" <scottc@MIT.Edu>,
        "'skanode@mit.edu'" <skanode@MIT.Edu>,
        "'strohon@mit.edu'"
	 <strohon@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
        "'tr6@mit.edu'" <tr6@MIT.Edu>, "'jdoucett@mit.edu'" <jdoucett@MIT.Edu>,
        "'tdoyle@mit.edu'" <tdoyle@MIT.Edu>,
        Jack Allen <jrallen@PLANT.MIT.EDU>,
        Tim Donaghey <TDonaghe@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
        "'nmorriso@mit.edu'"
	 <nmorriso@MIT.Edu>
Date: Wed, 31 Oct 2001 09:02:46 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	C-Zone; Cust-Coach; dfucillo@mit.edu; fenner@mit.edu;
> magowen@mit.edu; mamullow@mit.edu; mgibson@mit.edu; patdixon@mit.edu;
> rlbras@mit.edu; schedule@mit.edu; scottc@mit.edu; skanode@mit.edu;
> strohon@mit.edu; shutdowns@mit.edu; tr6@mit.edu; jdoucett@mit.edu;
> tdoyle@mit.edu; Jack Allen; Tim Donaghey
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; nmorriso@mit.edu
> Subject: 	Bldg. 1 - Asbestos Removal Notification
> 
> 
The following asbestos removal notification for Bldg. 1 - 090 on Wednesday,
11/7 through Friday, 11/9 is for your information.  If you have any question
about this, please contact either Tammy Doyle at 3-5166 or Jack Allen at
3-6352.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 1 - 090
> Date: 11/7/2001
> Day: Wednesday
> Time: 7 AM (11/7) - 4 PM (11/9)
> System: None - asbestos removal notification
> Duration: 57 hours
> Reason: 
> Must remove 20 square feet of floor tile in 1-090.
> 
> Effect: 
> No access to 1-090 during the asbestos removal period.
> 
> 