[57075] in Hotline Meeting
Bldg. 9 - Air Handler 1/Supply Fan 1/Return Fan 1 Shutdown Reques
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 30 08:08:43 2001
Message-ID: <568F0AEE7A57D511923900508B556451155E21@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'deedc@mit.edu'" <deedc@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'jobrien@mit.edu'" <jobrien@MIT.Edu>,
"'kirky@ceci.mit.edu'"
<kirky@ceci.mit.edu>,
"'mcurtin@mit.edu'" <mcurtin@MIT.Edu>,
"'mlavalle@mitvma.mit.edu'" <mlavalle@mitvma.mit.edu>,
"'ndk@mit.edu'"
<ndk@MIT.Edu>,
"'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
"'randy@mit.edu'" <randy@MIT.Edu>, "'sexton@mit.edu'" <sexton@MIT.Edu>,
"'src@mit.edu'" <src@MIT.Edu>, "'westlund@mit.edu'" <westlund@MIT.Edu>,
"'wjfitz@mit.edu'" <wjfitz@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>,
"'lordjim@mit.edu'" <lordjim@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 30 Oct 2001 08:08:40 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; Cust-Coach; deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu;
> kirky@ceci.mit.edu; mcurtin@mit.edu; mlavalle@mitvma.mit.edu; ndk@mit.edu;
> pam@ceci.mit.edu; randy@mit.edu; sexton@mit.edu; src@mit.edu;
> westlund@mit.edu; wjfitz@mit.edu; shutdowns@mit.edu; lordjim@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 9 - Air Handler 1/Supply Fan 1/Return Fan 1 Shutdown
> Request
>
>
The following shutdown request for Bldg. 9 - Floors 2 through 6 (Air Handler
1/Supply Fan/Return Fan 1 on Monday, 11/5 is for your information and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 9 - Floors 2 through 6
> Date: 11/5/2001
> Day: Monday
> Time: 5 AM - 9 AM
> System: Air Handler 1/Supply Fan 1/Return Fan 1
> Duration: 4 hours
> Reason:
> Replace motor sheave and speed-up fan.
>
> Effect:
> Loss of supply ventilation (air from outside), supply cooling (from
> ceiling supply fans) and supply heating (from ceiling supply fans) and
> return fan-1 in Bldg. 9 - floors2 through 6 during the 4-hour shutdown
> period.
>
>