[57016] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 66 - Revised Critical Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 25 14:16:54 2001

Message-ID: <568F0AEE7A57D511923900508B556451155DEB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patsys@mit.edu'" <patsys@mit.edu>,
        "'swetzel@mit.edu'"
	 <swetzel@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 25 Oct 2001 14:16:49 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	patsys@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 66 - Revised Critical Chilled Water Shutdown Request
> 
> 
The following revised Critical chilled water shutdown request for Bldg. 66 -
056, 060, 064 and 080 (offices, computer room and Athena Lab) on Monday,
10/29 is once agin for your review and comment.  Would you please let me
know if this new time better fits in with your schedules.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Critical
> Building: 66 - 056, 060, 064 and 080
> Date: 10/29/2001
> Day: Monday
> Time: 10 AM - 4 PM
> System: Chilled Water
> Duration: 6 hours
> Reason: 
> To move chilled water lines for installation of new steam meter below.
> 
> Effect: 
> Loss of chilled water (air conditioning) in the above-mentioned rooms
> during the 6-hour shutdown period. The air conditioning will remain on in
> these rooms until shutdown time in order for  cooling to remain in the
> rooms for several hours.
> 
> 

home help back first fref pref prev next nref lref last post