Bldg. 66 - Critical Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 24 09:39:34 2001

Message-ID: <568F0AEE7A57D511923900508B556451155DCB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patsys@mit.edu'" <patsys@mit.edu>,
        "'swetzel@mit.edu'"
	 <swetzel@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 24 Oct 2001 09:38:10 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	patsys@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 66 - Critical Chilled Water Shutdown Request
> 
> 
The following Critical chilled water shutdown request for Bldg. 66 -056,
060, 064 and 080 (offices, computer room and Athena Lab) on Monday, 10/29 is
for your information and comment.  Would you please let me know whether this
does or does not have your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872 

> Status: Critical
> Building: 66 - 056, 060, 064 and 080
> Date: 10/29/2001
> Day: Monday
> Time: 8 AM - 4 PM
> System: Chilled Water
> Duration: 8 hours
> Reason: 
> To move chilled water lines for installation of new steam meter below.
> 
> Effect: 
> Loss of chilled water in the above-mentioned rooms during the 8-hour
> shutdown period.
> 
> 