[56949] in Hotline Meeting
Re: Bldg. 66 - Sanitary Drainage Shutdown Request
daemon@ATHENA.MIT.EDU (Steve Wetzel)
Fri Oct 19 12:46:33 2001
Message-Id: <200110191646.MAA14104@melbourne-city-street.mit.edu>
Date: Fri, 19 Oct 2001 12:50:38 -0400
To: Andrea Nichols <andrea@PLANT.MIT.EDU>, A-Zone <A-Zone@MIT.EDU>,
Cust-Coach <cust-coach@MIT.EDU>,
"'kkgleasn@mit.edu'" <kkgleasn@MIT.EDU>,
"'patsys@mit.edu'" <patsys@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
From: Steve Wetzel <swetzel@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
In-Reply-To: <568F0AEE7A57D511923900508B556451155D89@PLANT.MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
Andrea
This shutdown is one that I think should be scheduled for off hours. My
suggestion would be an 11:00 PM to 7:00 AM time slot.
Steve
At 12:30 PM 10/19/2001 -0400, Andrea Nichols wrote:
>> To: A-Zone; Cust-Coach; kkgleasn@mit.edu; patsys@mit.edu;
>> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
>> Cc: shutdown@plant.mit.edu
>> Subject: Bldg. 66 - Sanitary Drainage Shutdown Request
>>
>>
>The following sanitary drainage shutdown request for Bldg. 66 - all
>bathrooms on Thursday, 10/25 is for your review and comment. Would you
>please let me know whether this does or does not have your approval.
>
>Thank you.
>
>Andrea Nichols
>Repair and Maintenance
>8-7872
>
>> Status: Normal
>> Building: 66 - all bathrooms
>> Date: 10/25/2001
>> Day: Thursday
>> Time: 3 PM - 11 PM
>> System: Sanitary Drainage
>> Duration: 8 hours
>> Reason:
>> Installing new building waste drain and vent.
>>
>> Effect:
>> Loss of sanitary drainage to bathrooms during the shutdown period.
>>
>>
>