[56924] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 18 - Critical Emergency Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 18 13:24:12 2001

Message-ID: <568F0AEE7A57D511923900508B556451155D6C@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rjwilk@mit.edu'" <rjwilk@mit.edu>, "'mbj@mkt.edu'" <mbj@mkt.edu>,
        "'crg@mit.edu'" <crg@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 18 Oct 2001 13:24:00 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	rjwilk@mit.edu; mbj@mkt.edu; crg@mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 18 - Critical Emergency Power Shutdown Request
> 
> 
The following Critical emergency power shutdown request for Bldg. 18 on
Thursday, 10/25 PM to Friday, 10/26 AM is for your information and comment.
Would you please let me know whether this does or does not have your
appoval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Critical
> Building: 18 - building to be evacuated during shutdown
> Date: 10/25/2001
> Day: Thursday
> Time: 9:30 PM (10/25) - 8:30 AM (10/26)
> System: Emergency Power
> Duration: 11 hours
> Reason: 
> To tie into emergency power activating emergency switchgear. The building
> is to be evacuated during the shutdown period.
> 
> Effect: 
> Loss of emergency power, elevators, computers, lighting in corridors and
> hallways, lab waste drainage, sanitary and storm drain drainage as well as
> the fire alarm system. 
> 
> 

home help back first fref pref prev next nref lref last post