[56922] in Hotline Meeting
Bldgs. 34, 36 and 38 Critical Emergency Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 18 12:58:02 2001
Message-ID: <568F0AEE7A57D511923900508B556451155D6A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'rroscoe@mit.edu'" <rroscoe@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>,
"'agallant@mit.edu'"
<agallant@MIT.Edu>,
"'pmorley@mit.edu'" <pmorley@MIT.Edu>,
"'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 18 Oct 2001 12:57:52 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; rroscoe@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; amcgurl@rle.mit.edu; agallant@mit.edu; pmorley@mit.edu;
> wrgibbs@rle.mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 34, 36 and 38 Critical Emergency Power Shutdown
> Request
>
>
The following Critical Emergency Powre shutdown request for Bldgs. 34, 36
and 38 on Wednesday, 10/24 is for your information and comment. Would you
please let me know whether this does or does not have your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Critical
> Building: 34, 36 and 38
> Date: 10/24/2001
> Day: Wednesday
> Time: 8 AM - 8:30 AM
> System: Emergency Power
> Duration: 5 minutes within 30 minute time frame
> Reason:
> Switchover emergency power to normal power, brief 5 minute interruption to
> elevators, stairway lighting.
>
> Effect:
> Brief 5 minute interruption of power to elevators, stairway lighting. If
> computers have been plugged into emergency power - they will be affected
> also.
>
>