Bldg. 50 - Rescheduled Low Pressure Steam Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 15 13:51:05 2001

Message-ID: <568F0AEE7A57D511923900508B556451155D2B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'MuddyJoeC@hotmail.com'" <MuddyJoeC@hotmail.com>,
        A-Zone
	 <A-Zone@MIT.Edu>, "'acameron@mit.edu'" <acameron@MIT.Edu>,
        "'acomeron@mit.edu'" <acomeron@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, "'eisen@mit.edu'" <eisen@MIT.Edu>,
        "'ekm@mit.edu'" <ekm@MIT.Edu>, "'mwf@mit.edu'" <mwf@MIT.Edu>,
        "'pwalsh@mit.edu'" <pwalsh@MIT.Edu>,
        "'rberlin@mit.edu'" <rberlin@MIT.Edu>,
        "'schedule@mit.edu'"
	 <schedule@MIT.Edu>,
        "'station-manager@wmbr.mit.edu'"
	 <station-manager@TURNTABLE.mit.edu>,
        "'w1mx-officers@mit.edu'"
	 <w1mx-officers@MIT.Edu>,
        "'wganger@mit.edu'" <wganger@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 15 Oct 2001 13:50:49 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	MuddyJoeC@hotmail.com; A-Zone; acameron@mit.edu; acomeron@mit.edu;
> Cust-Coach; eisen@mit.edu; ekm@mit.edu; mwf@mit.edu; pwalsh@mit.edu;
> rberlin@mit.edu; schedule@mit.edu; station-manager@wmbr.mit.edu;
> w1mx-officers@mit.edu; wganger@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 50 - Rescheduled Low Pressure Steam Shutdown Request
> 
> 
The following rescheduled low pressure steam shutdown request for Bldg. 50
now for Monday, 10/22, Tuesday, 10/23 and Wednesday, 10/24 is again for your
review and comment.  Would you please let me know if these new dates meet
with your approval or do not. (The initial dates were 10/17 - 10/19).

Thank you again for your time.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 50
> Date: 10/22/2001
> Day: Monday
> Time: 6 AM  - 3 PM each day
> System: Low pressure steam/all perimeter heating
> Duration: 3 days (9 hours each day)
> Reason: 
> Change steam traps and controls on the radiators.
> 
> Effect: 
> Loss of perimeter heating (steam radiators only) in Bldg. 50 during the
> shutdown period. This will not affect steam kettles.
> 
> 