[56798] in Hotline Meeting
Bldg. 66 - Approved Building Power Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 10 07:09:38 2001
Message-ID: <568F0AEE7A57D511923900508B556451155CE6@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'swetzel@mit.edu'" <swetzel@mit.edu>,
"'patsys@mit.edu'"
<patsys@mit.edu>,
"'ghand@mit.edu'" <ghand@mit.edu>,
"'nmorriso@mit.edu'" <nmorriso@mit.edu>,
Paul Stordy
<PStordy@PLANT.MIT.EDU>,
James Sullivan <jsulliva@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>, A-Zone <A-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Date: Wed, 10 Oct 2001 07:09:34 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: swetzel@mit.edu; patsys@mit.edu; ghand@mit.edu; nmorriso@mit.edu;
> Paul Stordy; James Sullivan; Manuel Moreira
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; A-Zone; Cust-Coach;
> shutdowns@mit.edu
> Subject: Bldg. 66 - Approved Building Power Shutdown
>
>
The following approved building power shutdown for Bldg. 66 - Magnet Lab
only on Saturday, 10/13 is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 56 - Magnet Lab
> Date: 10/13/2001
> Day: Saturday
> Time: 7 AM - 3 PM
> System: Building Power
> Duration: 8 hours
> Reason:
> Relocating remaining circuit panels SP1 thru SP5 to SP5 (for existing
> circuits).
>
> Effect:
> Loss of building power in 66 - Magnet Lab only. This means if there is a
> computer or lighting in the Magnet Lab - they will be inoperable during
> the shutdown period.
>
>