[56779] in Hotline Meeting
Emergency shutdown for building 39 on 10/9
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Oct 9 08:37:12 2001
Message-ID: <568F0AEE7A57D511923900508B5564519DD4CD@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: armay@mit.edu, B-Zone <B-Zone@mit.edu>, Cust-Coach
<cust-coach@mit.edu>,
George Mac Leod <gmacleod@mit.edu>, mcgrath@mtl.mit.edu,
rcf@space.mit.edu, walsh@mtl.mit.edu, schedule@mit.edu,
shutdowns@mit.edu, cpcommand@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Tue, 9 Oct 2001 08:37:05 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: armay@mit.edu; B-Zone; Cust-Coach; George Mac Leod;
> mcgrath@mtl.mit.edu; rcf@space.mit.edu; walsh@mtl.mit.edu;
> schedule@mit.edu; shutdowns@mit.edu; cpcommand@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Emergency shutdown for building 39 on 10/9
>
>
The following emergency shutdown for building 39 on 10/9 is for your
information.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Emergency
> Building: 39
> Date: 10/9/01
> Day: Tuesday
> Time: 8 am - 12 pm
> System: Processed Hot Lab Water
> Duration: 4 hours
> Reason:
> There is a broken nipple on the discharge side of the pump.
>
> Effect:
> There will be no process hot lab water.
>
>