[56741] in Hotline Meeting
Bldg. 37 - Domestic Hot Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 4 09:52:27 2001
Message-ID: <568F0AEE7A57D511923900508B556451155CB4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'alvarso@mit.edu'" <alvarso@mit.edu>, B-Zone <B-Zone@mit.edu>,
"'benford@space.mit.edu'" <benford@space.mit.edu>,
"'cmo@space.mit.edu'"
<cmo@space.mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'droberts@mit.edu'" <droberts@mit.edu>,
"'gallant@mit.edu'"
<gallant@mit.edu>,
"'kane@mit.edu'" <kane@mit.edu>,
"'murphy@space.mit.edu'" <murphy@space.mit.edu>,
"'politano@mit.edu'"
<politano@mit.edu>,
"'rcf@space.mit.edu'" <rcf@space.mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'slbrown@MIT.EDU'"
<slbrown@mit.edu>,
"'wendell@mit.edu'" <wendell@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 4 Oct 2001 09:52:24 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: alvarso@mit.edu; B-Zone; benford@space.mit.edu; cmo@space.mit.edu;
> Cust-Coach; droberts@mit.edu; gallant@mit.edu; kane@mit.edu;
> murphy@space.mit.edu; politano@mit.edu; rcf@space.mit.edu;
> schedule@mit.edu; slbrown@MIT.EDU; wendell@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 37 - Domestic Hot Water Shutdown Request
>
>
The following domestic hot water shutdown request for Bldg. 37 on Tuesday,
10/9 is for your information and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 37
> Date: 10/9/2001
> Day: Tuesday
> Time: 6 AM - 7 AM
> System: Domestic Hot Water
> Duration: 1 hour
> Reason:
> Cut and cap one recirculating line in 5th floor construction area (Reading
> Room).
>
> Effect:
> Loss of hot domestic water (water for bathroom and kitchen sink faucets)
> during the 1-hour shutdown period.
>
>