Bldg. 18 - Revised Approved Air Handler 1/Supply Fans 1- 5 Critic

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 3 12:49:51 2001

Message-ID: <568F0AEE7A57D511923900508B556451155CA3@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rjwilk@mit.edu'" <rjwilk@mit.edu>, "'mbj@mit.edu'" <mbj@mit.edu>,
        "'crg@mit.edu'" <crg@mit.edu>, Joe Collins <JCollins@PLANT.MIT.EDU>,
        Gerry Desmond <gdesmond@PLANT.MIT.EDU>,
        "'crendog@mit.edu'"
	 <crendog@mit.edu>, A-Zone <A-Zone@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>,
        Billy Homeyer <whomeyer@PLANT.MIT.EDU>,
        "'nmorriso@mit.edu'" <nmorriso@mit.edu>,
        Cust-Coach <cust-coach@mit.edu>, "'tr6@mit.edu'" <tr6@mit.edu>,
        "'jdoucett@mit.edu'" <jdoucett@mit.edu>
Date: Wed, 3 Oct 2001 12:49:41 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	rjwilk@mit.edu; mbj@mit.edu; crg@mit.edu; Joe Collins; Gerry
> Desmond; crendog@mit.edu; A-Zone
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; shutdowns@mit.edu;
> Billy Homeyer; nmorriso@mit.edu; Cust-Coach; tr6@mit.edu; jdoucett@mit.edu
> Subject: 	Bldg. 18 - Revised Approved Air Handler 1/Supply Fans 1- 5
> Critical Shutdown Request
> 
> 
The following revised approved Critical shutdown  for Bldg. 18 (Air Handler
1/Supply Fans 1 thru 5 (Exhaust and Return Fans remain on) now on Wednesday,
10/3 PM - Thursday, 10/4 AM - Thursday, 10/4 PM - Friday, 10/5 AM and
Friday, 10/5 PM to Saturday, 10/6 AM is for your information.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Critical
> Building: 18
> Date: 10/3/2001
> Day: Wednesday
> Time: 4 PM (10/3) - 6 AM (10/4) - 4 PM (10/4) - 6 AM (10/5) - 4 PM (10/5)
> - 12 noon (10/6)
> System: Air Handler 1/Supply Fans 1 - 5
> Duration: 3 days (14 hours each day except 10/6)
> Reason: 
> Asbestos abatement rework of heating steam piping, cleaning and filter
> replacement --filter replacement will take place on Saturday, 10/6.
> 
> Effect: 
> Loss of supply ventilation and supply cooling during the shutdown periods.
> 
> 