Bldg. 45 Air Handler 1/Return Fan 2 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 3 10:08:19 2001

Message-ID: <568F0AEE7A57D511923900508B556451155C9C@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.Edu>, "'scrowley@mit.edu'" <scrowley@MIT.Edu>,
        "'tweidner@MIT.EDU'" <tweidner@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 3 Oct 2001 10:08:11 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	D-Zone; scrowley@mit.edu; tweidner@MIT.EDU; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 45 Air Handler 1/Return Fan 2 Shutdown Request
> 
> 
The following shutdown request for Bldg. 45 - Air Handler 1/Return fan 2
(supply ventilation, supply cooling) on Tuesday, October 9 is for your
information and comment.  Would you please let me know whether this does or
does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 45 - East Side & Conference Rooms
> Date: 10/9/2001
> Day: Tuesday
> Time: 7:30 AM - 1:30 PM
> System: Air Handler 2 & Return Fan 2
> Duration: 6 hours
> Reason: 
> Clean constant volume boxes and coils to improve air flow to Conference
> Rooms.
> 
> Effect: 
> No access to rooms 125, 151 and 152 during the shutdown period. Rooms must
> be vacant during this period.
> 
> 