[56673] in Hotline Meeting
NW13 - Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 1 11:43:13 2001
Message-ID: <568F0AEE7A57D511923900508B556451155C6B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'actinide@mit.edu'" <actinide@mit.edu>, D-Zone <D-Zone@mit.edu>,
"'devries@mit.edu'" <devries@mit.edu>,
"'eslau@mit.edu'" <eslau@mit.edu>, "'fafrey@mit.edu'" <fafrey@mit.edu>,
"'fredmcw@mit.edu'"
<fredmcw@mit.edu>,
"'galanek@mit.edu'" <galanek@mit.edu>,
"'ginipig@MIT.EDU'" <ginipig@mit.edu>,
"'jbernard@mit.edu'"
<jbernard@mit.edu>,
"'jcyanch@mit.edu'" <jcyanch@mit.edu>,
"'kczer@MIT.EDU'" <kczer@mit.edu>,
"'klnoyes@MIT.EDU'" <klnoyes@mit.edu>,
"'politano@mit.edu'" <politano@mit.edu>,
"'safety@mit.edu'"
<safety@mit.edu>,
"'wendell@mit.edu'" <wendell@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
Warren Scott
<WScott@PLANT.MIT.EDU>,
"'nmorriso@mit.edu'" <nmorriso@mit.edu>, "'tr6@mit.edu'" <tr6@mit.edu>,
"'jdoucett@mit.edu'" <jdoucett@mit.edu>,
"'tdoyle@mit.edu'" <tdoyle@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Mon, 1 Oct 2001 11:41:43 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: actinide@mit.edu; D-Zone; devries@mit.edu; eslau@mit.edu;
> fafrey@mit.edu; fredmcw@mit.edu; galanek@mit.edu; ginipig@MIT.EDU;
> jbernard@mit.edu; jcyanch@mit.edu; kczer@MIT.EDU; klnoyes@MIT.EDU;
> politano@mit.edu; safety@mit.edu; wendell@mit.edu; shutdowns@mit.edu;
> Warren Scott; nmorriso@mit.edu; tr6@mit.edu; jdoucett@mit.edu;
> tdoyle@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: NW13 - Asbestos Removal Notification
>
>
The following asbestos removal notification for Bldg. NW13 - Roof SouthEast
corner Cooling Tower fill and eliminators on Tuesday, 10/16 through
Thursday, 10/18 is for your information. If you have any question about
this, please contact Tammy Doyle at 3-5166
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: NW13 - Roof SouthEast Cooling Tower
> Date: 10/16/2001
> Day: Tuesday
> Time: 7 AM (10/16) - 4 PM (10/18)
> System: None - asbestos removal notification
> Duration: 57 hours
> Reason:
> Must remove 100 cubic feet of floor tile from NW13 Roof - SouthEast corner
> fill and eliminators.
>
> Effect:
> No access to NW13 Roof - SouthEast corner cooling tower during asbestos
> removal period.
>
>