[56572] in Hotline Meeting
Bldg. 18 - Approved Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Sep 24 11:31:59 2001
Message-ID: <568F0AEE7A57D511923900508B556451155BFC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jcollins@mit.edu'" <jcollins@mit.edu>,
"'nmorriso@mit.edu'"
<nmorriso@mit.edu>,
"'safety@mit.edu'" <safety@mit.edu>,
James Sullivan
<jsulliva@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
Paul Stordy <PStordy@PLANT.MIT.EDU>
Cc: Operators <Operators@PLANT.MIT.EDU>, RM-Utl <rm-utl@mit.edu>,
"'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>, A-Zone <A-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Date: Mon, 24 Sep 2001 11:31:50 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: jcollins@mit.edu; nmorriso@mit.edu; safety@mit.edu; James Sullivan;
> Manuel Moreira; Paul Stordy
> Cc: Operators; RM-Utl; shutdown@plant.mit.edu; rm-shutdown@mit.edu;
> A-Zone; Cust-Coach; shutdowns@mit.edu
> Subject: Bldg. 18 - Approved Building Power Shutdown Request
>
>
The following approved building power shutdown request for Bldg. 18 (120/208
Electric Panels in Phase 2 and 3 Penthouses (exhaust fans) on Tuesday, 9/25
is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 18
> Date: 9/25/2001
> Day: Tuesday
> Time: 6 AM - 7 AM
> System: Building Power (120/208 Electric Panels in Phase 2 and 3
> Penthouses (Exhaust Fans)
> Duration: 1 hour
> Reason:
> Need to energize new Phase 1 electric panels.
>
> Effect:
> Loss of building power (120/208 Electric Panels in Phase 2 and 3
> Penthouses (exhaust fans) during the 1-hour shutdown period.
>
>