[56519] in Hotline Meeting
Bldg. 9 - Fire Alarm Live Audible Testing/UL Test
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 20 13:26:30 2001
Message-ID: <568F0AEE7A57D511923900508B556451155BC7@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'deedc@mit.edu'" <deedc@mit.edu>, "'gallant@mit.edu'"
<gallant@mit.edu>,
"'jobrien@mit.edu'" <jobrien@mit.edu>,
"'kirky@ceci.mit.edu'" <kirky@ceci.mit.edu>,
"'mlavalle@mitvma.mit.edu'"
<mlavalle@mitvma.mit.edu>,
"'ndk@mit.edu'" <ndk@mit.edu>, "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
"'randy@mit.edu'"
<randy@mit.edu>,
"'sexton@mit.edu'" <sexton@mit.edu>, "'src@mit.edu'"
<src@mit.edu>,
"'westlunc@mit.edu'" <westlunc@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 20 Sep 2001 13:26:20 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu; kirky@ceci.mit.edu;
> mlavalle@mitvma.mit.edu; ndk@mit.edu; pam@ceci.mit.edu; randy@mit.edu;
> sexton@mit.edu; src@mit.edu; westlunc@mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 9 - Fire Alarm Live Audible Testing/UL Test
>
>
The following fire alarm Live Audible Test/UL Test for Building 9 on Monday,
9/24 is for your information and comment. Would you please let me know
whether this does or does not have your approval.
Thank you
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 9
> Date: 9/24/2001
> Day: Monday
> Time: 6 AM - 12 Noon
> System: Fire Alarm
> Duration: 6 hours
> Reason:
> Live audible testing of the fire alarm system - UL test.
>
> Effect:
> Loss of fire alarm system during the testing period. The Safety Office
> will be advised of this. If there is a problem in you area, please dial
> X100 to report it.
>
>