[56403] in Hotline Meeting
Bldg. 4 - Cooling Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 13 12:35:47 2001
Message-ID: <568F0AEE7A57D511923900508B556451155B5E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ghughes@mit.edu'" <ghughes@mit.edu>,
"'glabonte@mit.edu'"
<glabonte@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 13 Sep 2001 12:32:47 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: ghughes@mit.edu; glabonte@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 4 - Cooling Shutdown Request
>
>
The following chilled water/supply cooling to Bldg .4 - 031 (DMSE) and 4 -
035 (Athena) on Tuesday, 9/18 is for your review and comment. Would you
please let me know whether this does or does not have your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 4 - 031 and 035
> Date: 9/18/2001
> Day: Tuesday
> Time: 7 AM - 3 PM
> System: Cooling to rooms
> Duration: 8 hours
> Reason:
> Replace valve, increase pipe size to Fan Coil Unit in 4-031.
>
> Effect:
> Losss of cooling to 4-031 and 035 during the shutdown period.
>
>