Bldg. 13 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Sep 10 13:17:26 2001
Message-ID: <568F0AEE7A57D511923900508B556451155B24@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'elk@mit.edu'" <elk@MIT.Edu>, "'schedule@mit.edu'" <schedule@MIT.Edu>,
"'src@mit.edu'" <src@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 10 Sep 2001 13:14:32 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; elk@mit.edu; schedule@mit.edu; src@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 13 - Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. 13 - 5011, 5027,
5027A, 5047, 5051, 5079, 5095, 5099, 5119, 5127, 5143, 5147 and 5101 on
Tuesday, 9/18, Wednesday, 9/19, Thursday, 9/20 and Friday, 9/21 is for your
information and comment. Would you please let me know whether this does or
does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 13 - 5011, 5027, 5027A, 5047, 5051, 5079, 5095, 5099, 5119,
> 5127, 5143, 5147 and 5101
> Date: 9/18/2001
> Day: Tuesday
> Time: 6 AM ((9/18) - 2 PM (9/21)
> System: Chilled Water
> Duration: 4 days (96 hours)
> Reason:
> To relocate center corridor mains for new ductwork.
>
> Effect:
> Loss of chilled water (air conditioning) in the above listed rooms only
> during the shutdown period.
>
>