[56327] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldgs. 44, 45 and 48 Critical Domestic Hot Water, All Steam Shutd

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Sep 10 08:05:55 2001

Message-ID: <568F0AEE7A57D511923900508B556451155B15@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-Utl <rm-utl@mit.edu>, D-Zone <D-Zone@mit.edu>,
        "'fisherp@mit.edu'"
	 <fisherp@mit.edu>,
        "'khewitt@mit.edu'" <khewitt@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>, B-Zone <B-Zone@mit.edu>,
        "'eliser@mit.edu'" <eliser@mit.edu>,
        "'scrowley@mit.edu'"
	 <scrowley@mit.edu>,
        "'tweidner@mit.edu'" <tweidner@mit.edu>,
        "'mistetri@mit.edu'" <mistetri@mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@mit.edu>,
        "'sfrankel@mit.edu'" <sfrankel@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        Joe Comoletti
	 <jcomolet@PLANT.MIT.EDU>,
        George Herald <gherald@PLANT.MIT.EDU>
Date: Mon, 10 Sep 2001 08:03:04 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	RM-Utl; D-Zone; fisherp@mit.edu; khewitt@mit.edu; shutdowns@mit.edu;
> B-Zone; eliser@mit.edu; scrowley@mit.edu; tweidner@mit.edu;
> mistetri@mit.edu; schedule@mit.edu; sfrankel@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Joe Comoletti; George
> Herald
> Subject: 	Bldgs. 44, 45 and 48 Critical Domestic Hot Water, All Steam
> Shutdown Announcement
> 
> 
The following Critical domestic hot water, all steam shutdown for Bldg. 44,
All steam shtudown for bldg. 45 and 48 heating hot water (already off) in
Bldg. 45 and 48 on Tuesday, 9/11 is for your information.

If you have any question about tis, pleae contact Joe Comoletti at 3-1500.

Thank you.

Andrea Nichols
Repair and Maintenane
8-7872

> Status: Critical
> Building: 44, 45 and 48
> Date: 9/11/2001
> Day: Tuesday
> Time: 8 AM - 6 PM
> System: Domestic Hot Water, Heating hot Water, All Steam and Condensate
> Return
> Duration: 12 hours
> Reason: 
> Repair steam main and condensate main valve.
> 
> Effect: 
> Loss of hot domestic water for bathroom and kitchen sink faucets in Bldg.
> 44 only, and all steam (heating hot water, supply heating (not on in
> summer time in Bldgs. 45 and 48) during the 12-hour shutdown period.
> 
> 