[56243] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 2 - Chilled Water/Supply Cooling Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 5 11:44:39 2001

Message-ID: <568F0AEE7A57D511923900508B556451155ADC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'capozzi@math.mit.edu'"
	 <capozzi@math.mit.edu>,
        "'crg@mit.edu'" <crg@MIT.Edu>, Cust-Coach
	 <cust-coach@MIT.Edu>,
        "'duggins@math.mit.edu'" <duggins@math.mit.edu>,
        "'mbj@mit.edu'" <mbj@MIT.Edu>, "'rjwilk@mit.edu'" <rjwilk@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'sdimond@mit.edu'"
	 <sdimond@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 5 Sep 2001 11:41:56 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	C-Zone; capozzi@math.mit.edu; crg@mit.edu; Cust-Coach;
> duggins@math.mit.edu; mbj@mit.edu; rjwilk@mit.edu; schedule@mit.edu;
> sdimond@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 2 - Chilled Water/Supply Cooling Shutdown Request
> 
> 
The following chilled water/supply cooling shutdown request for Bldg. 2 -
285, ziggurat area and floors 3, 4 and 5 on Friday, 9/7 is for your review
and comment.  Would you please let me know whether this does or does not
meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 2 - 285, ziggurat area, and floros 3, 4 and 5
> Date: 9/7/2001
> Day: Friday
> Time: 6 AM - 11 AM
> System: Chilled Water/Supply Cooling
> Duration: 5 hours
> Reason: 
> To cut and relocate chilled water piping as part of 2-285 renovation.
> 
> Effect: 
> Loss of chilled water (air conditioning) and supply cooling via ceiling
> supply fans in the areas mentioned above during the shutdown period.
> 
> 

home help back first fref pref prev next nref lref last post