[56233] in Hotline Meeting
Bldg. 68 - All Process Water and Lab Waste Drainage Shutdown Requ
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 5 10:02:03 2001
Message-ID: <568F0AEE7A57D511923900508B556451155AD4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'wplynch@mit.edu'" <wplynch@mit.edu>,
"'jfucillo@mit.edu'"
<jfucillo@mit.edu>,
"'jmganno@mit.edu'" <jmganno@mit.edu>,
"'maureen@mit.edu'" <maureen@mit.edu>,
"'rberlin@mit.edu'"
<rberlin@mit.edu>,
"'shyoung@mit.edu'" <shyoung@mit.edu>,
"'wganger@mit.edu'" <wganger@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 5 Sep 2001 09:59:15 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: wplynch@mit.edu; jfucillo@mit.edu; jmganno@mit.edu; maureen@mit.edu;
> rberlin@mit.edu; shyoung@mit.edu; wganger@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 68 - All Process Water and Lab Waste Drainage Shutdown
> Request
>
>
The following all hot and cold lab process water, de-ionized water and lab
waste drainage shutdown request for Bldg. 68 on Saturday, 9/8 is for your
information and comment. Would you please let me know whether this does or
does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 68
> Date: 9/8/2001
> Day: Saturday
> Time: 6 AM - 4 PM
> System: Hot and cold lab process water, de-ionized watre and lab waste
> drainage
> Duration: 10 hours
> Reason:
> To install a new flow meter to monitor the wastewater effluent.
>
> Effect:
> Loss of hot and cold lab process water, de-ionized water and lab waste
> drainage during the 10-hour shutdown period.
>
>