[56209] in Hotline Meeting
Bldg. 35 - Critical Air Handler 1 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 4 10:50:46 2001
Message-ID: <568F0AEE7A57D511923900508B556451155ABE@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'gerwent@mit.edu'"
<gerwent@MIT.Edu>,
"'inslee@mit.edu'" <inslee@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'stiffler@mit.edu'"
<stiffler@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 4 Sep 2001 10:48:02 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; gallant@mit.edu; gerwent@mit.edu;
> inslee@mit.edu; schedule@mit.edu; stiffler@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 35 - Critical Air Handler 1 Shutdown Request
>
>
The following Critical Air Handler 1 shutdown request for Bldg. 35 -
basement and 1st floors on Wednesday, 9/5 to Thursday, 9/6 PM is for your
information and comment. Would you please let me know whether this does or
does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 35 - basement and 1st floor
> Date: 9/5/2001
> Day: Wednesday
> Time: 7:30 AM (9/5) - 2:30 PM (9/6)
> System: Air Handler 1 PM#702311 (fresh air ventilation)
> Duration: 31 hours
> Reason:
> Repair to steam coil.
>
> Effect:
> Loss of fresh air ventilation in Bldg. 35 - basement and 1st floors during
> the shutdown period.
>
>