[56153] in Hotline Meeting
Bldg. N10 and N16 City Water Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 29 09:22:15 2001
Message-ID: <568F0AEE7A57D511923900508B556451155A66@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-PipeSys <rm-pipesys@mit.edu>, "'cmcooke@mit.edu'" <cmcooke@mit.edu>,
D-Zone <D-Zone@mit.edu>, "'ryan@mit.edu'" <ryan@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'armay@mit.edu'"
<armay@mit.edu>,
George Mac Leod <gmacleod@mit.edu>,
"'mmahoney@mit.edu'" <mmahoney@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
Jack Allen
<jrallen@PLANT.MIT.EDU>,
"'vcrayton@mit.edu'" <vcrayton@mit.edu>,
"'cp-command@mit.edu'" <cp-command@mit.edu>,
"'safety@mit.edu'"
<safety@mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Wed, 29 Aug 2001 09:19:41 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: RM-PipeSys; cmcooke@mit.edu; D-Zone; ryan@mit.edu;
> shutdowns@mit.edu; armay@mit.edu; George Mac Leod; mmahoney@mit.edu
> Cc: shutdown@plant.mit.edu; Jack Allen; vcrayton@mit.edu;
> cp-command@mit.edu; safety@mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. N10 and N16 City Water Shutdown
>
>
The following City Water shutdown for Bldgs. N10 and N16 on Thursday, 8/30
from 7 AM - 4 PM is for your information. If you have any question about
this, please contact either Jack Allen at 3-6352 or Vaughn Crayton at
3-5898.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: N10 and N16
> Date: 8/30/2001
> Day: Thursday
> Time: 7 AM - 4 PM
> System: City Water
> Duration: 8 hours within above time frame
> Reason:
> Cambridge Public Works capping off line on Mass. Ave. and Albany Street.
>
> Effect:
> Loss Hot and cold domestic water (no toilets, bathroom or kitchen sink
> faucets), hot and cold lab process water (no water for lab equipment
> requiring use of same) or heating hot water (not used in summer) during
> the 8 hour shutdown period in Bldgs. N10 and N16.
>
>