[56111] in Hotline Meeting
Bldg. 8 - Fire Alarm Tie-In and Testing
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Aug 24 13:18:08 2001
Message-ID: <568F0AEE7A57D511923900508B556451155A32@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'carolr@mit.edu'" <carolr@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'ghughes@mit.edu'" <ghughes@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'kmartel@mit.edu'"
<kmartel@MIT.Edu>,
"'lechtman@mit.edu'" <lechtman@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>,
Howard Harrison <HHarriso@PLANT.MIT.EDU>,
John Denucce <jdenucce@PLANT.MIT.EDU>,
Tom Connolly
<tconnoll@PLANT.MIT.EDU>,
David Ferrante <dferrant@PLANT.MIT.EDU>,
"'safety@mit.edu'" <safety@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>, C-Zone <C-Zone@MIT.Edu>,
Billy Homeyer <whomeyer@PLANT.MIT.EDU>,
Ron Catella
<rcatella@PLANT.MIT.EDU>
Date: Fri, 24 Aug 2001 13:15:41 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; carolr@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; kmartel@mit.edu; lechtman@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; Howard Harrison; John Denucce; Tom Connolly; David
> Ferrante; safety@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; C-Zone; Billy Homeyer;
> Ron Catella
> Subject: Bldg. 8 - Fire Alarm Tie-In and Testing
>
>
The following Fire Alarm tie-in and live audible testing for Bldg. 8 - 4th
floor on Monday, 8/27 is for your information. If you have any concern
about this, please contact Ron Catella at 8-6811.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 8 - 4th floor and rest of building
> Date: 8/27/2001
> Day: Monday
> Time: 9 AM - 11 AM
> System: Fire Alarm
> Duration: 2 hours
> Reason:
> Tie-in fire alarm at panel followed by live audible testing.
>
> Effect:
> Live audible testing of building fire alarm system.
>
> All alarms heard before and after this time period should be considered
> actual alarms and occupants should follow the building evacuation plan.
>
>