[56103] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 5 - Asbestos Removal Notification/Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 23 13:56:57 2001

Message-ID: <568F0AEE7A57D511923900508B556451155A1D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'arhodes@mit.edu'" <arhodes@mit.edu>, C-Zone <C-Zone@mit.edu>,
        "'ctaylor@mit.edu'" <ctaylor@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
        "'engler@mitvma.mit.edu'" <engler@mitvma.mit.edu>,
        "'fenner@mit.edu'"
	 <fenner@mit.edu>,
        "'honda@mit.edu'" <honda@mit.edu>, "'hover@mit.edu'"
	 <hover@mit.edu>,
        "'jmcollin@mit.edu'" <jmcollin@mit.edu>,
        "'kbarrett@mit.edu'" <kbarrett@mit.edu>, "'mad@mit.edu'" <mad@mit.edu>,
        "'mamullow@mit.edu'" <mamullow@mit.edu>,
        "'mgibson@mit.edu'"
	 <mgibson@mit.edu>,
        "'mleen@mit.edu'" <mleen@mit.edu>,
        "'peggyb@mit.edu'"
	 <peggyb@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'sclinton@mit.edu'" <sclinton@mit.edu>,
        "'scottc@mit.edu'"
	 <scottc@mit.edu>,
        "'sgeorge@mit.edu'" <sgeorge@mit.edu>,
        "'skendall@mit.edu'" <skendall@mit.edu>,
        "'skendall@mit.edu'"
	 <skendall@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'tr6@mit.edu'" <tr6@mit.edu>, "'jdoucett@mit.edu'" <jdoucett@mit.edu>,
        "'tdoyle@mit.edu'" <tdoyle@mit.edu>,
        Frank Lewis <flewis@PLANT.MIT.EDU>,
        "'safety@mit.edu'" <safety@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Thu, 23 Aug 2001 13:54:26 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	arhodes@mit.edu; C-Zone; ctaylor@mit.edu; Cust-Coach;
> engler@mitvma.mit.edu; fenner@mit.edu; honda@mit.edu; hover@mit.edu;
> jmcollin@mit.edu; kbarrett@mit.edu; mad@mit.edu; mamullow@mit.edu;
> mgibson@mit.edu; mleen@mit.edu; peggyb@mit.edu; schedule@mit.edu;
> sclinton@mit.edu; scottc@mit.edu; sgeorge@mit.edu; skendall@mit.edu;
> skendall@mit.edu; shutdowns@mit.edu; tr6@mit.edu; jdoucett@mit.edu;
> tdoyle@mit.edu; Frank Lewis; safety@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: 	Bldg. 5 - Asbestos Removal Notification/Shutdown Request
> 
> 
The following asbestos removal notification/shutdown request for Bldg. 5 -
016 Outside Hall on Tuesday, 9/4 to Thursday, 9/6 is for your information.
If you have any question about this, please contact Tammy Doyle ata 3-5166.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 5 - 016 (outside Hall)
> Date: 9/4/2001
> Day: Tuesday
> Time: 7 AM (9/4) - 4 PM (9/6)
> System: None - asbestos removal notification
> Duration: 33 hours
> Reason: 
> Remove 15 feet of pipe insulation on Domestic Cold Water pipe.
> 
> Effect: 
> Loss of domestic cold water in 5 - 016 (Men's Lavatory) during the
> shutdown period. Area outside 5-016 where asbestos is being removed will
> be cordoned off during the asbestos removal period. 
> 
> 

home help back first fref pref prev next nref lref last post