Bldg. N51 and N52 - Bldg. Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 22 15:09:51 2001

Message-ID: <568F0AEE7A57D511923900508B556451155A07@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'arhodes@mit.edu'" <arhodes@mit.edu>,
        "'cbdewart@mit.edu'"
	 <cbdewart@mit.edu>, D-Zone <D-Zone@mit.edu>,
        "'honda@mit.edu'"
	 <honda@mit.edu>, "'mleen@mit.edu'" <mleen@mit.edu>,
        "'slb@mit.edu'"
	 <slb@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 22 Aug 2001 15:07:28 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	arhodes@mit.edu; cbdewart@mit.edu; D-Zone; honda@mit.edu;
> mleen@mit.edu; slb@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. N51 and N52 - Bldg. Power Shutdown Request
> 
> 
The following building power shutdown request for Bldgs. N51/N52 on
Thrusday, 8/30 PM to Friday, 8/31 AM is for your review and comment.  Would
you please let me know whether this does or does not meet with your
approval. The request was initially sent out for N52 on 8/15. It has been
advised that N51 would also be affected by this shutdown request,

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: N51/N52
> Date: 8/30/2001
> Day: Thursday
> Time: 8 PM (8/30) - 8 AM (8/31)
> System: Building Power
> Duration: 12 hours
> Reason: 
> Tie-in new switchgear.
> 
> Effect: 
> Loss of Power:  access controls (light switches, any equipment plugged
> into electrical outlets), building power, elevators, computers,
> lighting/corridors/stairs; Air:  supply ventilation (air from outside),
> supply cooling, exhaust-laboratory, exhaust-general, exhaust-toilet and
> compressed control air (all from ceiling supply fans) during the 12-hour
> shutdown period.
> 
> 