Bldg. 35 - Air Handler 1 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 22 09:17:56 2001
Message-ID: <568F0AEE7A57D511923900508B5564511559F6@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'gerwent@mit.edu'"
<gerwent@MIT.Edu>,
"'inslee@mit.edu'" <inslee@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'stiffler@mit.edu'"
<stiffler@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 22 Aug 2001 09:15:33 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; gallant@mit.edu; gerwent@mit.edu;
> inslee@mit.edu; schedule@mit.edu; stiffler@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 35 - Air Handler 1 Shutdown Request
>
>
The following shutdown request for Bldg. 35 - basement and 1st floors (Air
Handler 1) on Tuesday, 8/28 is for your review and comment. Would you
please let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 35 - basement and 1st floors
> Date: 8/28/2001
> Day: Tuesday
> Time: 7;30 AM - 3:30 PM
> System: Air Handler 1 - PM#702311
> Duration: 8 hours
> Reason:
> Repair leak in coils
>
> Effect:
> Loss of supply ventilation, supply cooling, and supply heating (off for
> summer) in 35 - basement and first floors during the shutdown period.
>
>