Bldg. 9 - Heating Hot Water Shutdown Cancelled

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 15 10:33:59 2001

Message-ID: <568F0AEE7A57D511923900508B556451155992@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'deedc@mit.edu'" <deedc@MIT.Edu>,
        "'gallant@mit.edu'" <gallant@MIT.Edu>,
        "'jobrien@mit.edu'" <jobrien@MIT.Edu>,
        "'kirky@ceci.mit.edu'"
	 <kirky@ceci.mit.edu>,
        "'mlavalle@mitvma.mit.edu'"
	 <mlavalle@mitvma.mit.edu>,
        "'ndk@mit.edu'" <ndk@MIT.Edu>, "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
        "'randy@mit.edu'"
	 <randy@MIT.Edu>,
        "'sexton@mit.edu'" <sexton@MIT.Edu>, "'src@mit.edu'"
	 <src@MIT.Edu>,
        "'westlund@mit.edu'" <westlund@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Date: Wed, 15 Aug 2001 10:31:45 -0400
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"

Dear Everyone:

The Heating Hot Water shutdown for Bldg. 9 - 1st floor - interior heating
and the hot deck for Floors 2 through 4 has been cancelled for now because
the parts have not arrived.

It is now requested that this shutdown work be rescheduled to next Tuesday,
8/21 from 6 AM to 2 PM.  Would you please let me know if this new date would
be all right or not.

Thank you again for your time,

Andrea Nichols
Repair and Maintenance
8-7872